Overhead door scope of work.
Scope of work to install doors windows at 65 leyard s road.
The work shall include but shall not necessarily be limited to the following.
All the work shall be in accordance with recognized us and international building and construction codes.
Construction shall abide by embassy rules and regulations including security and safety regulations.
This contract will be issued for overhead door repair and replacement work.
Inspect equipment for damaged missing or worn parts.
Four visits per year 1.
Public works procurement procedures will apply above this dollar threshold according to delaware code title 29 chapter 6960 sub chapter iv.
Replace any damaged missing or worn hardware.
Lube all moving parts.
Overhead doors rolling shutters description designer owner nrb g c others specify comments.
Scope of work the contractor should furnish everything needed to perform all of the requirements of this contract including without limitation all labour supervision tools materials equipment transportation permits licenses and supervision to maintain and repair and make alterations to these doors.
Provide all vehicles lifts and tools needed for the work.
Scope of work doors hardware alder street project 1 1 general a.
Maintain any professional licenses required to perform the work outlined in this request for proposal.
Shall be responsible for installation and making of all connections for each overhead door to be safe and operable.
The work consists of installing new embassy supplied doors and windows at 65 leyard s road a us embassy owned property.
Have and maintain a thorough knowledge of commercial overhead door systems and rolling gates.
The door opening should be reinforced studs for installation of the door frame.
Supply and install hp door opener for all garage overhead doors c w 2 remotes 3.
Work check list this detailed scope of work document can be used to ensure all elements of the modular off site construction project are captured and assigned to the project team including owner design professionals modular company general.
The size and scope of services will not exceed 50 000 00 per project or 15 000 00 for alteration repair or renovations.
Work the term work includes all labor materials equipment and services required of the contractor as shown described or inferred in the contract documents.
Inspect equipment and adjust as needed.
Install the new wall as per the drawings below wall type 2 up to the bottom of structure including 2 layers of 12 mm gypsum board 100 mm sound attenuation insulation.
Supply and install 16 x 7 four section non insulated overhead garage doors with 4 panels of glazing as per the plan and door schedule details 2.
Texas overhead door s preventative maintenance program call today for details.
Access to the fire trucks and associated.
The contractor is only to use its own forces and or owner construction manager approved sub trades to undertake.
On call preventative maintenance service and inspection.